GDh. Faresmaathodaa Airport Development (Land reclamation)
Project Status:
Completed
Expected Start Date: 01/01/2020
Start Date: 02/08/2018
Expected End Date:
Revised Expected End Date:
End Date::17/08/2019
Physical Work Dates
Expected Start Date of Physical Work:
Start Date of Physical Work: 02/08/2018
Expected End Date of Physical Work:
End Date of Physical Work: 17/08/2019
Last updated: 26/01/2023 10:48
Budget
- NIL
Expenditure
Func
|
Month
|
Year
|
Amount
|
|
Domestic
- Government of Maldives |
December |
2019
|
71,657,907.00
|
|
Domestic
- Government of Maldives |
November |
2020
|
7,456,385.29
|
|
|
79,114,292.29 |
|