Establishment Of Outdoor Gym - N.Maalhendhoo
Description:
ID:  
ISLES/1024
Expected Start Date:
Start Date: 25/08/2020
Expected End Date:
Revised Expected End Date:
End Date::16/09/2021
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
2023's Budget:  
MVR  0.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work: 10/04/2021
Expected End Date of Physical Work:
End Date of Physical Work: 16/09/2021
Challenges:
Last updated: 21/09/2021 12:49

Islands

Island Budget (MVR)
1 N. Maalhendhoo 253,591.00
253,591.00