Estab. Water & Sewerage System - HA.Molhadhoo
Description:
ID:  
ISLES/1100
Project Status:  
Contracted
Status Details:
Expected Start Date: 18/02/2021
Start Date: 28/02/2021
Expected End Date: 01/05/2023
Revised Expected End Date: 19/04/2023
End Date::
Funding:  
- Domestic ( Government of Maldives )
2021's Budget:  
MVR  7,341,600.00
2022's Budget:  
MVR  19,320,000.00
Physical Work Dates  
Expected Start Date of Physical Work: 25/11/2021
Start Date of Physical Work:
Expected End Date of Physical Work: 10/05/2023
End Date of Physical Work:
Challenges:
Last updated: 15/07/2021 13:37

Islands

Island Budget (MVR)
1 HA. Molhadhoo 41,152,356.00
41,152,356.00