Developing Breakwater & Quay Wall - B.Hithaadhoo
Description:
ID:  
ISLES/1140
Project Status:  
On-going
Status Details:
tendering stage
Expected Start Date: 30/05/2021
Start Date: 28/02/2022
Expected End Date: 25/11/2022
Revised Expected End Date:
End Date::
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
2022's Budget:  
MVR  3,389,709.00
2023's Budget:  
MVR  5,750,971.00
Physical Work Dates  
Expected Start Date of Physical Work: 01/01/2022
Start Date of Physical Work: 28/02/2022
Expected End Date of Physical Work: 25/11/2022
End Date of Physical Work:
Challenges:
Last updated: 22/11/2022 10:48

Islands

Island Budget (MVR)
1 B. Hithaadhoo 21,008,525.00
21,008,525.00