Establishing Water & Sewerage System - B.Kudarikilu
Description:
ID:  
ISLES/1143
Project Status:  
Contracted
Status Details:
Expected Start Date: 19/01/2022
Start Date: 29/12/2021
Expected End Date: 22/06/2023
Revised Expected End Date:
End Date::
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
2022's Budget:  
MVR  4,421,968.00
2023's Budget:  
MVR  3,135,063.00
Physical Work Dates  
Expected Start Date of Physical Work: 08/10/2022
Start Date of Physical Work: 08/10/2022
Expected End Date of Physical Work: 31/03/2023
End Date of Physical Work:
Challenges:
Last updated: 29/11/2022 11:57

Islands

Island Budget (MVR)
1 B. Kudarikilu 30,080,739.00
30,080,739.00