Establishing Water & Sewerage System - B.Dhonfanu
Description:
ID:  
ISLES/1148
Project Status:  
On-going
Status Details:
Expected Start Date: 19/01/2022
Start Date: 29/12/2021
Expected End Date: 22/06/2023
Revised Expected End Date:
End Date::
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
2022's Budget:  
MVR  4,259,399.00
2023's Budget:  
MVR  3,019,806.00
Physical Work Dates  
Expected Start Date of Physical Work: 19/01/2022
Start Date of Physical Work: 08/10/2022
Expected End Date of Physical Work: 22/06/2023
End Date of Physical Work:
Challenges:
Last updated: 29/11/2022 11:59

Islands

Island Budget (MVR)
1 B. Dhonfanu 29,666,651.00
29,666,651.00