Land Reclamation & Coastal Protection - K.Dhiffushi
Description:
ID:  
ISLES/1155
Project Status:  
Pre-tendering
Status Details:
Expected Start Date: 25/09/2021
Start Date:
Expected End Date:
Revised Expected End Date:
End Date::
Funding:  
- Domestic ( Government of Maldives )
2021's Budget:  
MVR  1,000,000.00
2022's Budget:  
MVR  31,467,450.00
Physical Work Dates  
Expected Start Date of Physical Work: 25/09/2021
Start Date of Physical Work:
Expected End Date of Physical Work: 25/09/2022
End Date of Physical Work:
Challenges:
Last updated: 19/10/2021 10:34

Islands

Island Budget (MVR)
1 K. Dhiffushi 71,334,900.00
71,334,900.00