Devel. Breakwater at Ferry Terminal - AA.Ukulhas
Description:
ID:  
ISLES/1160
Expected Start Date:
Start Date: 10/11/2020
Expected End Date: 10/11/2021
Revised Expected End Date: 12/02/2022
End Date::01/05/2022
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
Prject Budget:  
19925160
2023's Budget:  
MVR  652,274.00
2024's Budget:  
MVR  587,046.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work: 24/02/2021
Expected End Date of Physical Work: 12/02/2022
End Date of Physical Work: 01/05/2022
Challenges:
Last updated: 25/04/2023 21:39

Islands

Island Budget (MVR)
1 AA. Ukulhas 6,962,500.00
8,201,820.00