Estab. Water System - L.Maavah
Description:
ID:  
ISLES/1193
Project Status:  
On-going
Status Details:
Expected Start Date: 29/09/2019
Start Date: 29/09/2019
Expected End Date: 10/08/2021
Revised Expected End Date: 10/08/2021
End Date::
Funding:  
- Domestic ( Government of Maldives )
2021's Budget:  
MVR  10,385,272.00
2022's Budget:  
MVR  7,162,494.00
Physical Work Dates  
Expected Start Date of Physical Work: 15/04/2020
Start Date of Physical Work: 15/04/2020
Expected End Date of Physical Work: 07/06/2021
End Date of Physical Work:
Challenges:
Last updated: 15/09/2021 01:02

Islands

Island Budget (MVR)
1 L. Maavah 33,468,566.00
33,468,566.00