Contruction of MNPI Office Building
Description:
ID:  
ISLES/1232
Project Status:  
On-going
Status Details:
Expected Start Date:
Start Date: 21/10/2019
Expected End Date: 20/02/2021
Revised Expected End Date: 20/02/2023
End Date::
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
2022's Budget:  
MVR  10,360,963.00
2023's Budget:  
MVR  3,147,613.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work: 17/03/2020
Expected End Date of Physical Work: 20/02/2022
End Date of Physical Work:
Challenges:
Last updated: 10/10/2022 09:46

Islands

Island Budget (MVR)
1 Male' City Hulhumaale 195,069,960.00
195,069,960.00