Construction of Customs North Regional Head Office in Kulhudufushi
Description:
ID:  
ISLES/0002
Project Status:  
Completed
Status Details:
Expected Start Date: 24/10/2017
Start Date: 24/10/2017
Expected End Date: 27/11/2019
Revised Expected End Date: 27/11/2019
End Date::27/11/2019
Handling Agency:  
Maldives Customs Service
Funding:  
- Domestic
2021's Budget:  
MVR  0.00
Physical Work Dates  
Expected Start Date of Physical Work: 24/10/2017
Start Date of Physical Work: 24/10/2017
Expected End Date of Physical Work: 27/11/2019
End Date of Physical Work: 27/11/2019
Challenges:
Last updated: 30/08/2021 13:32

Islands

Island Budget (MVR)
1 HDh. Kulhudhuffushi 4,347,928.00
4,347,928.00