Upgrading of Habour - N.Miladhoo
Description:
ID:  
ISLES/0344
Expected Start Date:
Start Date: 09/10/2019
Expected End Date: 30/12/2021
Revised Expected End Date:
End Date::10/03/2022
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
Prject Budget:  
42183082
2023's Budget:  
MVR  2,047,942.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work: 26/11/2020
Expected End Date of Physical Work: 30/12/2021
End Date of Physical Work: 10/03/2022
Challenges:
Last updated: 25/04/2023 21:40

Islands

Island Budget (MVR)
1 N. Miladhoo 36,112,304.00
38,160,246.00