Land Reclamation - AA.Ukulhas
Description:
ID:  
ISLES/0359
Project Status:  
On-going
Status Details:
Expected Start Date:
Start Date: 01/10/2019
Expected End Date: 10/11/2022
Revised Expected End Date: 30/05/2023
End Date::
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
2023's Budget:  
MVR  10,544,927.00
2024's Budget:  
MVR  11,863,043.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work: 10/11/2020
Expected End Date of Physical Work: 30/05/2023
End Date of Physical Work:
Challenges:
Last updated: 26/02/2023 12:21

Islands

Island Budget (MVR)
1 AA. Ukulhas 19,217,117.00
54,375,575.00