V. Felidhoo Harbour
Description:
ID:  
ISLES/0404
Project Status:  
Completed
Status Details:
completed
Expected Start Date:
Start Date: 19/09/2019
Expected End Date: 30/07/2020
Revised Expected End Date: 30/08/2020
End Date::04/08/2020
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
Prject Budget:  
18508697
2022's Budget:  
MVR  955,163.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work: 26/12/2019
Expected End Date of Physical Work:
End Date of Physical Work: 04/08/2020
Challenges:
Last updated: 23/11/2021 08:55

Islands

Island Budget (MVR)
1 V. Felidhoo 15,255,914.00
15,255,914.00