Fuvahmulah Flat area Landscape and fence
Description:
ID:  
ISLES/0427
Expected Start Date: 20/10/2019
Start Date: 20/10/2019
Expected End Date: 25/06/2020
Revised Expected End Date: 07/12/2020
End Date::07/12/2020
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
2023's Budget:  
MVR  0.00
Physical Work Dates  
Expected Start Date of Physical Work: 20/10/2019
Start Date of Physical Work: 30/10/2019
Expected End Date of Physical Work: 31/10/2020
End Date of Physical Work: 07/12/2020
Challenges:
Last updated: 24/10/2021 09:42

Islands

Island Budget (MVR)
1 Fuvahmulah City Fuvahmulah 27,209,011.00
27,209,011.00