Estab. Water System (4 Islands) & Water Storage (25 Islands)
Description:
ID:  
ISLES/0470
Project Status:  
On-going
Status Details:
Expected Start Date: 23/03/2017
Start Date: 23/03/2017
Expected End Date: 23/03/2022
Revised Expected End Date: 23/03/2022
End Date::
Funding:  
- Grant ( Green Climate Fund )
- Trust Fund ( World Bank )
2021's Budget:  
MVR  0.00
Physical Work Dates  
Expected Start Date of Physical Work: 01/11/2018
Start Date of Physical Work: 01/11/2018
Expected End Date of Physical Work: 19/08/2021
End Date of Physical Work:
Challenges:
Last updated: 19/10/2021 12:26

Islands

Island Budget (MVR)
1 HDh. Nolhivaranfaru 0.00
2 Sh. Foakaidhoo 0.00
3 R. Maduvvari 0.00
4 B. Dharavandhoo 0.00
5 AA. Mathiveri 0.00
6 AA. Bodufolhudhoo 0.00
7 AA. Himendhoo 0.00
8 Adh. Kun'burudhoo 0.00
9 Adh. Dhigurah 0.00
10 M. Raiymandhoo 0.00
11 M. Veyvah 0.00
12 M. Naalaafushi 0.00
13 Dh. Meedhoo 0.00
14 Dh. Ban'didhoo 0.00
15 Dh. Hulhudheli 0.00
16 Th. Dhiyamigili 0.00
17 Th. Kan'doodhoo 0.00
18 Th. Vandhoo 0.00
19 Th. Gaadhiffushi 0.00
20 Th. Kin'bidhoo 0.00
21 Th. Omadhoo 0.00
22 GA. Maamendhoo 0.00
23 GA. Nilandhoo 0.00
24 GA. Kon'dey 0.00
25 GDh. Hoan'dehdhoo 0.00
26 GDh. Nadellaa 0.00
27 GDh. Rathafandhoo 0.00
28 GDh. Fiyoari 0.00
29 GDh. Faresmaathodaa 0.00
41,381,438.00