Finishing Of 105 Housing units - HDh.Kulhudhufushi
Description:
ID:  
ISLES/4720
Project Status:  
On-going
Status Details:
Expected Start Date:
Start Date: 06/04/2021
Expected End Date: 02/12/2021
Revised Expected End Date:
End Date::
Funding:  
- Domestic ( Government of Maldives )
2021's Budget:  
MVR  10,237,500.00
2022's Budget:  
MVR  37,537,500.00
Physical Work Dates  
Expected Start Date of Physical Work: 28/06/2021
Start Date of Physical Work: 28/06/2021
Expected End Date of Physical Work: 03/12/2022
End Date of Physical Work:
Challenges:
Last updated: 14/09/2021 13:23

Islands

Island Budget (MVR)
1 HDh. Kulhudhuffushi 68,250,000.00