GA. Maamendhoo Sewerage Sytem
Description:
ID:  
ISLES/0478
Project Status:  
On-going
Status Details:
Expected Start Date:
Start Date: 22/07/2018
Expected End Date: 19/05/2019
Revised Expected End Date: 04/02/2022
End Date::
Funding:  
- Domestic ( Government of Maldives )
- Trust Fund ( Maldives Green Fund )
2022's Budget:  
MVR  3,327,876.00
2023's Budget:  
MVR  500,449.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work: 22/07/2018
Expected End Date of Physical Work: 04/02/2022
End Date of Physical Work:
Challenges:
Last updated: 17/04/2022 13:34

Islands

Island Budget (MVR)
1 GA. Maamendhoo 49,684,285.00
49,684,285.00