1530 Social Housing Units in Hulhumalé Phase 2
Description:
ID:  
ISLES/4817
Project Status:  
On-going
Expected Start Date: 15/03/2018
Start Date: 15/03/2018
Expected End Date: 14/03/2020
Revised Expected End Date: 31/03/2022
End Date::
Funding:  
- Loan ( Seylan Bank Plc )
- Loan ( China Development Bank )
Prject Budget:  
2671515000
2022's Budget:  
MVR  0.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work: 15/03/2018
Expected End Date of Physical Work: 31/10/2022
End Date of Physical Work:
Challenges:
Last updated: 29/11/2022 10:44

Islands

Island Budget (MVR)
1 Male' City Hulhumaale 2,671,515,000.00
2,671,515,000.00