Establishment of Community Water Storage System.
Description:
ID:  
ISLES/0508
Project Status:  
Completed
Status Details:
Completed.
Expected Start Date: 21/06/2018
Start Date: 21/06/2018
Expected End Date: 31/10/2019
Revised Expected End Date:
End Date::31/12/2019
Funding:  
- Domestic
2021's Budget:  
MVR  0.00
Physical Work Dates  
Expected Start Date of Physical Work: 21/06/2018
Start Date of Physical Work: 21/06/2018
Expected End Date of Physical Work: 31/10/2019
End Date of Physical Work: 31/10/2019
Challenges:
Last updated: 25/11/2021 08:31

Islands

Island Budget (MVR)
1 Lh. Olhuvelifushi 19,748.00
2 AA. Maalhos 19,748.00
3 Th. Hirilandhoo 19,748.00
4 GDh. Madaveli 19,748.00
78,992.00