Development of Polytechnic Building - K.Thulusdhoo
Description:
ID:  
ISLES/6070
Project Status:  
Tendered
Status Details:
This project is planned to be developed under the public-private partnership model.
Expected Start Date: 31/10/2020
Start Date: 10/01/2020
Expected End Date: 31/07/2023
Revised Expected End Date:
End Date::
Handling Agency:  
Ministry of Higher Education
Funding:  
- Domestic ( Government of Maldives )
2022's Budget:  
MVR  200,000.00
2023's Budget:  
MVR  9,050,986.00
Physical Work Dates  
Expected Start Date of Physical Work: 01/01/2022
Start Date of Physical Work:
Expected End Date of Physical Work: 31/03/2023
End Date of Physical Work:
Challenges:
Last updated: 04/08/2022 12:33

Islands

Island Budget (MVR)
1 K. Thulusdhoo 18,787,785.00
18,787,785.00