Accelr. Sustainable Pvt. Invmt. in Renewable Energy - ASPIRE
Description:
ID:  
ISLES/0608
Project Status:  
On-going
Status Details:
Phase 1 (Installation of 1.5MW solar PV systems in Hulhumale’) has been completed and is in operation. Phase 2 (Installation of 5MW solar PV systems in Hulhumale-Hulhule’Link Road) State Electric Company ltd and Housing Development Corporation coordinating to handover the site to contactor (ENSIS). Phase 3 (Installation of 11 MW Land-based Solar PV at Addu City, Fuvahmulah City, Kulhudhuffushi City, Lh.Hinnavaru, Gdh.Thinadhoo and B.Eydhafushi) bid document is sent to those who was qualified .
Expected Start Date:
Start Date: 01/10/2014
Expected End Date: 31/03/2024
Revised Expected End Date:
End Date::
Funding:  
- Grant ( World Bank )
2022's Budget:  
MVR  0.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work: 19/03/2017
Expected End Date of Physical Work: 31/03/2024
End Date of Physical Work:
Challenges:
Last updated: 22/09/2022 09:09

Islands

Island Budget (MVR)
1 Male' City Male'
2 Male' City Hulhumaale
3 Fuvahmulah City Fuvahmulah
4 Addu City Hithadhoo
5 Addu City Feydhoo
6 Addu City Maradhoofeydhoo
7 B. Eydhafushi
8 Lh. Hinnavaru
9 Kulhudhuffushi City Kulhudhuffushi
10 GDh. Thinadhoo
73,337,875.00