Estab. Lighting at Football Ground - N.Holhudhoo
Description:
ID:  
ISLES/6293
Expected Start Date: 16/03/2022
Start Date: 10/06/2022
Expected End Date: 15/07/2022
Revised Expected End Date:
End Date::
Funding:  
- Domestic ( Government of Maldives )
2023's Budget:  
MVR  437,500.00
2024's Budget:  
MVR  1,000,000.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work: 10/06/2022
Expected End Date of Physical Work: 20/11/2022
End Date of Physical Work:
Challenges:
Last updated: 15/06/2023 11:20

Islands

Island Budget (MVR)
1 N. Holhudhoo 345,000.00
1,782,500.00