Development of Childrens Park - B.Kamadhoo
Description:
ID:  
ISLES/6357
Project Status:  
Contracted
Status Details:
Expected Start Date: 31/03/2022
Start Date:
Expected End Date: 31/07/2022
Revised Expected End Date:
End Date::
Funding:  
- Domestic ( Government of Maldives )
2022's Budget:  
MVR  75,000.00
2023's Budget:  
MVR  26,587.00
Physical Work Dates  
Expected Start Date of Physical Work: 28/09/2022
Start Date of Physical Work:
Expected End Date of Physical Work: 31/12/2022
End Date of Physical Work:
Challenges:
Last updated: 22/11/2022 20:42

Islands

Island Budget (MVR)
1 B. Kamadhoo 125,698.00
125,698.00