Afeefuhdheen School Boundary Wall
Description:
ID:  
ISLES/0065
Project Status:  
Completed
Status Details:
Expected Start Date: 30/09/2019
Start Date: 30/09/2019
Expected End Date:
Revised Expected End Date:
End Date::14/12/2019
Funding:  
- Domestic ( Government of Maldives )
2021's Budget:  
MVR  24,996.00
Physical Work Dates  
Expected Start Date of Physical Work: 30/09/2019
Start Date of Physical Work: 30/09/2019
Expected End Date of Physical Work:
End Date of Physical Work: 14/12/2019
Challenges:
Last updated: 19/01/2021 12:06

Islands

Island Budget (MVR)
1 HDh. Kulhudhuffushi 549,996.00
549,996.00