Construction of Mosque - R. Vaadhoo
Description:
ID:  
ISLES/0670
Project Status:  
Pre-tendering
Status Details:
Expected Start Date: 30/06/2021
Start Date: 01/07/2019
Expected End Date: 12/10/2021
Revised Expected End Date:
End Date::
Handling Agency:  
Ministry of Islamic Affairs
Funding:  
- Domestic ( Government of Maldives )
2021's Budget:  
MVR  2,009,893.00
2022's Budget:  
MVR  111,148.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work: 01/07/2019
Expected End Date of Physical Work: 12/10/2021
End Date of Physical Work:
Challenges:
Last updated: 16/06/2021 15:35

Islands

Island Budget (MVR)
1 R. Vaadhoo 5,445,936.00
5,445,936.00