Hulhumale Island Development Project
Description:
ID:  
ISLES/0683
Expected Start Date:
Start Date: 12/01/2017
Expected End Date: 30/08/2020
Revised Expected End Date: 30/08/2020
End Date::
Handling Agency:  
Ministry of Finance
Funding:  
- Loan ( Saudi Fund )
- Loan ( Saudi Fund )
2023's Budget:  
MVR  87,884,490.00
2024's Budget:  
MVR  33,287,849.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work: 12/01/2017
Expected End Date of Physical Work: 30/08/2020
End Date of Physical Work:
Challenges:
Last updated: 19/11/2023 12:10

Islands

Island Budget (MVR)
1 Male' City Hulhumaale 641,991,941.00
763,164,280.00