Construction of Immigration Office Building - S.Hithadhoo
Description:
ID:  
ISLES/0776
Project Status:  
Design Awarded
Status Details:
Expected Start Date: 01/10/2021
Start Date: 10/03/2020
Expected End Date: 05/05/2024
Revised Expected End Date:
End Date::
Handling Agency:  
Maldives Immigration
Funding:  
- Domestic ( Government of Maldives )
2021's Budget:  
MVR  420,000.00
2022's Budget:  
MVR  1,050,000.00
Physical Work Dates  
Expected Start Date of Physical Work:
Start Date of Physical Work:
Expected End Date of Physical Work:
End Date of Physical Work:
Challenges:
Last updated: 01/08/2021 12:30

Islands

Island Budget (MVR)
1 Addu City Hithadhoo 4,200,000.00
4,200,000.00