MJM School Building (Multi Purp. Hall) - Fuvamulak
Description:
ID:  
ISLES/0080
Project Status:  
Completed
Status Details:
Expected Start Date: 27/12/2019
Start Date: 27/12/2019
Expected End Date: 20/09/2021
Revised Expected End Date: 31/03/2021
End Date::18/09/2021
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
2022's Budget:  
MVR  381,804.00
Physical Work Dates  
Expected Start Date of Physical Work: 27/12/2019
Start Date of Physical Work: 27/12/2019
Expected End Date of Physical Work: 20/09/2021
End Date of Physical Work: 18/09/2021
Challenges:
Last updated: 24/10/2021 09:42

Islands

Island Budget (MVR)
1 Fuvahmulah City Fuvahmulah 7,933,318.00
7,933,318.00