School Building (6 Class & Hall) - K.Gulhi
Description:
ID:  
ISLES/0809
Expected Start Date: 15/08/2022
Start Date: 11/08/2022
Expected End Date: 01/05/2023
Revised Expected End Date: 31/10/2023
End Date::
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
2023's Budget:  
MVR  3,309,693.00
2024's Budget:  
MVR  3,723,404.00
Physical Work Dates  
Expected Start Date of Physical Work: 15/08/2022
Start Date of Physical Work: 11/08/2022
Expected End Date of Physical Work: 31/10/2023
End Date of Physical Work:
Challenges:
Last updated: 19/09/2023 10:19

Islands

Island Budget (MVR)
1 K. Gulhi 8,650,000.00
16,241,608.00