School Building (Office) - HDh.Atoll
Description:
ID:  
ISLES/0840
Expected Start Date: 20/04/2022
Start Date: 18/05/2022
Expected End Date: 30/09/2023
Revised Expected End Date:
End Date::
Funding:  
- Domestic ( Government of Maldives )
- Domestic ( Government of Maldives )
2023's Budget:  
MVR  550,000.00
2024's Budget:  
MVR  1,100,000.00
Physical Work Dates  
Expected Start Date of Physical Work: 20/04/2022
Start Date of Physical Work: 18/05/2022
Expected End Date of Physical Work: 30/09/2023
End Date of Physical Work:
Challenges:
Last updated: 19/09/2023 09:18

Islands

Island Budget (MVR)
1 Kulhudhuffushi City Kulhudhuffushi 4,275,000.00
5,925,000.00