Construction of emergency medical service centre
Description:
ID:  
ISLES/0926
Project Status:  
Completed
Status Details:
Expected Start Date: 17/10/2019
Start Date: 20/07/2020
Expected End Date: 05/02/2021
Revised Expected End Date: 30/04/2021
End Date::31/10/2021
Handling Agency:  
Ministry of Health
Funding:  
- Grant ( Government Of India )
Prject Budget:  
8450296
2021's Budget:  
MVR  2,535,089.00
2022's Budget:  
MVR  422,515.00
Physical Work Dates  
Expected Start Date of Physical Work: 25/07/2020
Start Date of Physical Work: 25/07/2020
Expected End Date of Physical Work: 31/10/2021
End Date of Physical Work: 31/10/2021
Challenges:
Last updated: 09/11/2021 11:22

Islands

Island Budget (MVR)
1 B. Dharavandhoo 5,945,390.00
5,945,390.00