Harbour Expansion Project - Kulhudhuffushi
Description:
ID:  
ISLES/0288
Expected Start Date:
Start Date: 26/12/2018
Expected End Date: 30/04/2021
Revised Expected End Date: 30/04/2021
End Date::30/04/2021
Funding:  
- Grant ( Asian Development Bank )
- Domestic ( Government of Maldives )
Prject Budget:  
160978021
2023's Budget:  
MVR  0.00
Physical Work Dates  
Expected Start Date of Physical Work: 26/12/2018
Start Date of Physical Work: 26/12/2018
Expected End Date of Physical Work: 20/03/2020
End Date of Physical Work: 30/04/2021
Challenges:
Last updated: 25/01/2023 16:24

Islands

Island Budget (MVR)
1 Kulhudhuffushi City Kulhudhuffushi 92,639,649.00
92,639,649.00