"Contract Terminated due to non-performance of the Contractor
To re-Advertise
Signed an MOU with Thinadhoo Council to manage the IWMC Construction project
Amending the drawings as per the new IWMC design concept
Agency:
Ministry of Environment, Climate Change and Technology
"MOU signed with the council.
Budget transfered
EMP Consultant evaluation completed, project award process ongoing . EMP Sent to EPA for reviewing
Detailed Engineering Documents completed.
Tender documents sent to council "
Agency:
Ministry of Environment, Climate Change and Technology
Phase 1 (Installation of 1.5MW solar PV systems in Hulhumale’) has been completed and is in operation.
Phase 2 (Installation of 5MW solar PV systems in Hulhumale-Hulhule’Link Road) State Electric Company ltd and Housing Development Corporation coordinating to handover the site to contactor (ENSIS).
Phase 3 (Installation of 11 MW Land-based Solar PV at Addu City, Fuvahmulah City, Kulhudhuffushi City, Lh.Hinnavaru, Gdh.Thinadhoo and B.Eydhafushi) bid document is sent to those who was qualified .
Agency:
Ministry of Environment, Climate Change and Technology
This project aims to establish a sustainable solid waste management system in the islands of Zone 3- AA. Adh. K. and V. The project is funded by ADB and other multilateral organisation and the Maldivian Government. 8 contracts have been awareded- 3 consultancies, 2 civil works, 6 goods..
Agency:
Ministry of Environment, Climate Change and Technology
Final works of Zone 2 RWMS operationalization ongoing. Technical and Financial Feasibility Study for Zone 4&5 RWMS still ongoing. Yet, World Bank clearance recently received for initiating island level insfrastructural works.
Agency:
Ministry of Environment, Climate Change and Technology
"MoU signed with the councils for work .
Budget transfered. Council has sent letter regarding how to proceed. Council requests for the provision of WM equipment; letter sent to finance in accordance to the request "
Agency:
Ministry of Environment, Climate Change and Technology
"Meeting with council held.
EMP extended.
Design and BOQ works ongoing. will be due on 9th April 2021
Budget transfer requested to MoF.
Civil Works Tendered, Bids recieved , Evaluation process ongoing "
Agency:
Ministry of Environment, Climate Change and Technology
"Waste to Energy facility contracted - Design approved, mechanical running test for the steam turbine done
Plant shipped on 4th Dec 2020 and arrived on 20th Dec 2020
Site handover date 1st May 2021
Site Mobilization - 1st July 2021
Plant 2nd shipment arriving 24th July 2021
Completed installation of temporary boundary fence(South, West, and North side – East side remains)
Completed soil excavation for equipment foundation"
Equipment foundations are complete
All remaining parts of the plant arrived in a chartered vessel to Hithadhoo port and were transferred to the project site
Plant Installation Ongoing
Agency:
Ministry of Environment, Climate Change and Technology
"Waste to Energy module at R. Vandhoo commissioning done and ongoing Monitoring / Troubleshooting
Additional procurements for operationalization of Vandhoo being carried out by the remaining project funds"
Agency:
Ministry of Environment, Climate Change and Technology
This project aims to establish a sustainable solid waste management system in the islands of Zone 3- AA. Adh. K. and V. The project is funded by ADB and other multilateral organization and the Maldivian Government. 3 contracts have been awarded- 2 consultancies (Independent Environment Monitor and Project Management Design Construction Supervision Consultants) , and 1 civil works (Design, Build Operate Waste to Energy Facility and K. Thilafushi).
Agency:
Ministry of Environment, Climate Change and Technology
Works finished as per the contract. Council has requested for additional works through the variation option. requested the council to make decision through its bid comittee
Agency:
Ministry of Environment, Climate Change and Technology